On this page you will find examples of 120 Ton annual production facilities 
This is not a standard.
Hesy aquaculture supplies production facilities in a range from 1 till 10.000 T.
The species listed below are just a selection of the potential culturable fish.

Eel:

   

Typical Draft set-up for a 120 tonnes Eel system

Price for technical instalations in Euros at request
Total required building  1200 m2
Minimum height in building 3.0 meter
Electricity demand 55 kW/h
Electricity demand for oxygen production and heating/cooling  at request
Possible average feeding 485 kg/day
Average FCR (Feed conversion) 1.3
Annual production days 365 days
New intake water maximum 30.000 m3/year 100 m3/day (average)
Estimated glass-eel input 300 kg
Fish output at 150 grams (120.000 kg per year) 800.000 pcs
Estimated price for 1 kg glass-eel at request
Estimated price for each kg eel at request
Calculated price to produce a kilogram of eel
Nursery optional
at request

Pike perch/ European Perch :

  

Typical Draft set-up for a 120 tonnes pike perch/ perch system

Price for technical installations in Euros at request
Total required building  1800 m2
Minimum height in building 3 meter
Electricity demand 65 kW/h
Electricity demand for oxygen production and heating/cooling  at request
Possible average feeding 485 kg/day
Average FCR (Feed conversion) 1.3
Annual production days 365 days
New intake water maximum 30.000 m3/year 100 m3/day (average)
Estimated fish input at 10 grams 130.000 pcs
Fish output at 1000 grams (120.000 kg per year) 120.000 pcs
Estimated price for each fish of 3 gram at request
Estimated price for each kg fish of 800 gram at request
Calculated price to produce a kilogram of fish
Hatchery - Nursery optional
at request

Trout : 

  

Typical Draft set-up for a 120 tonnes trout system

Price for technical installations in Euros at request
Total required building  1000 m2
Minimum height in building 3 meter
Electricity demand 45 kW/h
Electricity demand for oxygen production and heating/cooling  at request
Possible average feeding 360 kg/day
Average FCR (Feed conversion) 1.1
Annual production days 365 days
New intake water maximum 25.000 m3/year 70 m3/day (average)
Estimated fish input at 5 grams 400.000 pcs
Fish output at 333 grams (120.000 kg per year) 360.000 pcs
Estimated price for each fish of 5 gram at request
Estimated price for each kg fish of 333 gram at request
Calculated price to produce a kilogram of fish
Hatchery - Nursery optional
at request

Sturgeon:  

  

Typical Draft set-up for a 120 tonnes Sturgeon system

Price for technical installations in Euros at request
Total required building  1800 m2
Minimum height in building 3 meter
Electricity demand 60 kW/h
Electricity demand for oxygen production and heating/cooling  at request
Possible average feeding 485 kg/day
Average FCR (Feed conversion) 1.3
Annual production days 365 days
New intake water maximum 25.000 m3/year 100 m3/day (average)
Estimated fish input at 5 grams 70.000 pcs
Fish output at 2000 grams (120.000 kg per year) 60.000 pcs
Estimated price for each fish of 5 gram at request
Estimated price for each kg fish of 333 gram at request
Calculated price to produce a kilogram of fish
Hatchery - Nursery - caviar production optional
at request

Tilapia:

  

Typical Draft set-up for a 120 tonnes Tilapia system

Price for technical installations in Euros at request
Total required building  1250 m2
Minimum height in building 3 meter
Electricity demand 40 kW/h
Electricity demand for oxygen production and heating/cooling at request
Possible average feeding 400 kg/day
Average FCR (Feed conversion) 1.2
Annual production days 365 days
New intake water maximum 28.000 m3/year 75 m3/day (average)
Estimated fish input at 5 grams 160.000 pcs
Fish output at 800 grams (120.000 kg per year) 150.000 pcs
Estimated price for each fish of 5 gram at request
Estimated price for each kg fish of 800 gram at request
Calculated price to produce a kilogram of fish
Hatchery - Nursery optional
at request

Sea bream/ bass farm:

  

Typical Draft set-up for a 120 tonnes Sea bream and Sea bass system

Price for technical installations in Euros at request
Total required building  1600 m2
Minimum height in building 3 meter
Electricity demand 50 kW/h
Electricity demand for oxygen production and heating/cooling  at request
Possible average feeding 485 kg/day
Average FCR (Feed conversion) 1.3
Annual production days 365 days
New intake water maximum 30.000 m3/year 100 m3/day (average)
Estimated fish input at 5 grams 260.000 pcs
Fish output at 500 grams (120.000 kg per year) 240.000 pcs
Estimated price for each fish of 5 gram at request
Estimated price for each kg fish of 800 gram at request
Calculated price to produce a kilogram of fish
Hatchery - Nursery optional
at request

No rights can be derived from above mentioned figures